Relocating Guildford Sewage Treatment Works
Relocating Guildford Sewage Treatment Works
Planning Application Documents
July 2022 update
In December 2021 we submitted a planning application to Surrey County Council for the relocation of Guildford Sewage treatment works (STW).
Surrey County Council are now holding a third period of public consultation following our submission of further information to address comments from consultees. You can view the submitted information and comments on Surrey County Council's website Any comments must be submitted to Surrey County Council by 29th August 2022. We cannot take your comments on the application documents.
All of the further information submitted to Surrey County Council is available below to download and view. They are all less than 10MB to help with downloading and to meet planning application validation requirements.
All comments on the planning application must be submitted to Surrey County Council on their website – Thames Water cannot accept your comments on the planning application.
North Moors Pedestrian Crossing
Regulation 25 Further Information
Environmental Statement Addendum
ES Addendum Appendix A - Figures
ES Addendum Appendix C - Land Stability
ES Addendum Appendix B - Envirocheck Report 2022-Part1of23
ES Addendum Appendix B - Envirocheck Report 2022-Part2of23
ES Addendum Appendix B - Envirocheck Report 2022-Part3of23
ES Addendum Appendix B - Envirocheck Report 2022-Part4of23
ES Addendum Appendix B - Envirocheck Report 2022-Part5of23
ES Addendum Appendix B - Envirocheck Report 2022-Part6of23
ES Addendum Appendix B - Envirocheck Report 2022-Part7of23
ES Addendum Appendix B - Envirocheck Report 2022-Part8of23
ES Addendum Appendix B - Envirocheck Report 2022-Part9of23
ES Addendum Appendix B - Envirocheck Report 2022-Part10of23
ES Addendum Appendix B - Envirocheck Report 2022-Part11of23
ES Addendum Appendix B - Envirocheck Report 2022-Part12of23
ES Addendum Appendix B - Envirocheck Report 2022-Part13of23
ES Addendum Appendix B - Envirocheck Report 2022-Part14of23
ES Addendum Appendix B - Envirocheck Report 2022-Part15of23
ES Addendum Appendix B - Envirocheck Report 2022-Part16of23
ES Addendum Appendix B - Envirocheck Report 2022-Part17of23
ES Addendum Appendix B - Envirocheck Report 2022-Part18of23
ES Addendum Appendix B - Envirocheck Report 2022-Part19of23
ES Addendum Appendix B - Envirocheck Report 2022-Part20of23
ES Addendum Appendix B - Envirocheck Report 2022-Part21of23
ES Addendum Appendix B - Envirocheck Report 2022-Part22of23
ES Addendum Appendix B - Envirocheck Report 2022-Part23of23
Email re: Guildford STW Relocation Factual Report
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part1
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part2
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part3
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part4
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part5
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part6
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part7
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part8
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part9
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part10
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part11
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part12
Guildford STW Relocation Ground Investigation Report (GESL) Final_Part13
Planning Application Documents
June 2022 update
In December 2021 we submitted a planning application to Surrey County Council for the relocation of Guildford Sewage treatment works (STW).
Surrey County Council are now undertaking a further period of public consultation following our submission of further information to address comments from consultees. You can view the submitted information and comments on Surrey County Council on their website Any comments must be submitted to Surrey County Council by 6th July 2022. We cannot take your comments on the application documents.
All of the further information submitted to Surrey County Council is available below to download and view below. They are all less than 10MB to help with downloading and to meet planning application validation requirements.
All comments on the planning application must be submitted to Surrey County Council on their website – Thames Water cannot accept your comments on the planning application.
Response to Landscape Comments
Response to Historic Environment Comments
Response to Geological and Geotechnical Comments
Response to Environment Agency Comments
Revised Schedule of Buildings and Structures
Illustrative Environmental Masterplan
Revised ES Appendix 9.4 – Visualisations (Part 1 of 4)
Revised ES Appendix 9.4 – Visualisations (Part 2 of 4)
Revised ES Appendix 9.4 – Visualisations (Part 3 of 4)
Revised ES Appendix 9.4 – Visualisations (Part 4 of 4)
Response to Air Quality Comments (March)
December 2021
All of the planning application documents submitted to Surrey County Council in December 2021 are available below to download and view. They are all less than 10MB to help with downloading and to meet planning application validation requirements.
All comments on the planning application must be submitted to Surrey County Council on their website – Thames Water cannot accept your comments on the planning application.
An overview of the project is provided on Thames Waters website here
01 J009-AJ-GUILS1ZZ-PLN-DR-C-10500 P02 SITE LOCATION PLAN
02 J009-AJ-GUILS1ZZ-PLN-DR-C-10501 P03 EXISTING SITE LAYOUT OVERVIEW
03 J009-AJ-GUILS1ZZ-PLN-DR-C-10522 P03 EXISTING SITE LAYOUT NEW STW
04 J009-AJ-GUILS1ZZ-PLN-DR-C-10512 P03 DEMOLITION PLAN
05 J009-AJ-GUILS1ZZ-PLN-DR-C-10502 P03 PROPOSED SITE LAYOUT OVERVIEW
06 J009-AJ-GUILS1ZZ-PLN-DR-C-10523 P03 PROPOSED SITE LAYOUT STW
07 J009-AJ-GUILS1ZZ-PLN-DR-C-10704 P02 PROPOSED SECTIONS AND ELEVATIONS LOCATION PLAN
08 J009-AJ-GUILS1ZZ-PLN-DR-C-10528 P03 PROPOSED SITE ELEVATIONS
09 J009-AJ-GUILS1ZZ-PLN-DR-C-10527 P03 PROPOSED LONG SECTIONS
10 J009-AJ-GUILS1ZZ-PLN-DR-C 10705 P03 PROPOSED LONG SECTIONS WITH TREES
11 J009-AJ-GUILS1ZZ-PLN-DR-C-10629 P04 WELFARE BUILDING ROOF PLAN AND ELEVATIONS
12 J009-AJ-GUILS1ZZ-PLN-DR-C-10630 P03 WELFARE BUILDING FLOOR PLANS
13 J009-AJ-GUILS1ZZ-PLN-DR-C-10529 P03 INLET PUMPING STATION (SHAFT E2) PLAN AND ELEVATIONS
14 J009-AJ-GUILS1ZZ-PLN-DR-C-10538 P04 INLET WORKS PLAN
15 J009-AJ-GUILS1ZZ-PLN-DR-C-10539 P03 INLET WORKS ELEVATIONS
17 J009-AJ-GUILS1ZZ-PLN-DR-C-10545 P03 PRIMARY SETTLEMENT TANKS PLAN & ELEVATIONS
18 J009-AJ-GUILS1ZZ-PLN-DR-C-10549 P04 PST SLUDGE PUMPING STATION 1 PLAN & ELEVATIONS
19 J009-AJ-GUILS1ZZ-PLN-DR-C-10552 P03 PST SLUDGE PUMPING STATION 2 PLAN & ELEVATIONS
20 J009-AJ-GUILS1ZZ-PLN-DR-C-10555 P03 STORM TANKS PLAN AND ELEVATIONS
21 J009-AJ-GUILS1ZZ-PLN-DR-C-10561 P03 ACTIVATED SLUDGE PLANT DISTRIBUTION CHAMBER PLAN & ELEVATIONS
22 J009-AJ-GUILS1ZZ-PLN-DR-C-10565 P03 ACTIVATED SLUDGE PLANT PLAN & ELEVATIONS
23 J009-AJ-GUILS1ZZ-PLN-DR-C-10566 P03 ACTIVATED SLUDGE PLANT BLOWERS PLAN AND ELEVATIONS
24 J009-AJ-GUILS1ZZ-PLN-DR-C-10569 P04 FINAL SETTLEMENT TANKS DISTRIBUTION CHAMBER PLAN & ELEVATIONS
25 J009-AJ-GUILS1ZZ-PLN-DR-C-10573 P03 FINAL SETTLEMENT TANKS PLAN
26 J009-AJ-GUILS1ZZ-PLN-DR-C-10574 P03 FINAL SETTLEMENT TANKS ELEVATIONS
27 J009-AJ-GUILS1ZZ-PLN-DR-C-10576 P03 RAS/SAS PUMPING STATION PLAN AND ELEVATIONS
28 J009-AJ-GUILS1ZZ-PLN-DR-C-10579 P03 CLOTH PILE FILTERS DISTRIBUTION CHAMBER PLAN & ELEVATIONS
29 J009-AJ-GUILS1ZZ-PLN-DR-C-10583 P03 CLOTH PILE FILTERS PLAN & ELEVATIONS
30 J009-AJ-GUILS1ZZ-PLN-DR-C-10590 P03 FERRIC DOSING PLANT PLAN AND ELEVATIONS
31 J009-AJ-GUILS1ZZ-PLN-DR-C-10594 P03 PRIMARY SCUM RETURN PUMPING STATION PLAN AND ELEVATIONS
32 J009-AJ-GUILS1ZZ-PLN-DR-C-10600 P03 PRIMARY SLUDGE & SAS SLUDGE HOLDING TANKS PLAN & ELEVATIONS
33 J009-AJ-GUILS1ZZ-PLN-DR-C-10608 P03 SLUDGE IMPORT TANK PLAN AND ELEVATIONS
34 J009-AJ-GUILS1ZZ-PLN-DR-C-10612 P03 SLUDGE THICKENING & DEWATERING PLANT PLAN AND ELEVATIONS
35 J009-AJ-GUILS1ZZ-PLN-DR-C-10616 P03 SLUDGE THICKENING AND BLENDING TANKS PLAN
36 J009-AJ-GUILS1ZZ-PLN-DR-C-10617 P03 SLUDGE THICKENING AND BLENDING TANKS ELEVATIONS
37 J009-AJ-GUILS1ZZ-PLN-DR-C-10620 P03 SLUDGE LIQUOR BALANCING TANK PLAN AND ELEVATIONS
38 J009-AJ-GUILS1ZZ-PLN-DR-C-10659 P03 SLUDGE CAKE STORAGE SILO/HOPPER PLAN & ELEVATIONS
39 J009-AJ-GUILS1ZZ-PLN-DR-C-10635 P03 ODOUR CONTROL PLANT 1 – INLET WORKS/ PSTS PLAN & ELEVATIONS
40 J009-AJ-GUILS1ZZ-PLN-DR-C-10638 P03 ODOUR CONTROL PLANT 2 – SLUDGE TREATMENT PLAN & ELEVATIONS
41 J009-AJ-GUILS1ZZ-PLN-DR-C-10641 P03 POTABLE WATER BOOSTER SET PLAN AND ELEVATIONS
42 J009-AJ-GUILS1ZZ-PLN-DR-C-10644 P03 MCC1 AND SUB-STATION – INLET WORKS PLAN & ELEVATIONS
43 J009-AJ-GUILS1ZZ-PLN-DR-C-10647 P02 MCC2 AND SUB-STATION - PST & TT PLAN & ELEVATIONS
44 J009-AJ-GUILS1ZZ-PLN-DR-C-10650 P03 MCC3 AND SUB-STATION – ASP PLAN & ELEVATIONS
45 J009-AJ-GUILS1ZZ-PLN-DR-C-10653 P03 MCC4 AND SUB-STATION - SLUDGE TREATMENT PLAN & ELEVATIONS
46 J009-AJ-GUILS1ZZ-PLN-DR-C-10656 P03 MCC5 - FST PLAN & ELEVATIONS
47 J009-AJ-GUILS1ZZ-PLN-DR-C-10666 P03 STANDBY GENERATORS PLAN & ELEVATIONS
48 J009-AJ-GUILS1ZZ-PLN-DR-C-10632 P03 FUEL STORAGE TANKS PLAN & ELEVATIONS
49 J009-AJ-GUILS1ZZ-PLN-DR-C-10694 P02 UKPN COMPOUND ACCESS JUNCTION LAYOUT
50 J009-AJ-GUILS1ZZ-PLN-DR-C-10663 P03 MAIN ELECTRICAL INTAKE SUB-STATION PLAN & ELEVATIONS
51 J009-AJ-GUILS1ZZ-PLN-DR-C-10696 P04 WESTERN ACCESS JUNCTION LAYOUT
52 J009-AJ-GUILS1ZZ-PLN-DR-C-10695 P03 EASTERN ACCESS JUNCTION LAYOUT
53 J009-AJ-GUILS1ZZ-PLN-DR-C-10700 P03 WESTERN ACCESS GATE DETAIL
54 J009-AJ-GUILS1ZZ-PLN-DR-C-10701 P03 EASTERN ACCESS GATE DETAILS
55 J009-AJ-GUILS1ZZ-PLN-DR-C-10702 P03 FENCING STANDARD DETAILS
56 J009-AJ-GUILS1ZZ-PLN-DR-C-10526 P04 PROPOSED STW DRAINAGE PLAN
57 J009-AJ-GUILS1ZZ-PLN-DR-C-10673 P02 EAST SURFACE WATER PUMPING STATION PLAN AND ELEVATIONS
58 J009-AJ-GUILS1ZZ-PLN-DR-C-10674 P02 WEST SURFACE WATER PUMPING STATION PLAN AND ELEVATIONS
59 J009-AJ-GUILS1ZZ-PLN-DR-C-10503 P04 PROPOSED OUTFALL PIPELINE PLAN
60 J009-AJ-GUILS1ZZ-PLN-DR-C-10504 P04 OUTFALL PIPELINE LONG SECTION
61 J009-AJ-GUILS1ZZ-PLN-DR-C-10505 P04 OUTFALL STRUCTURE
62 J009-AJ-GUILS1ZZ-PLN-DR-C-10507 P04 TRANSFER TUNNEL ROUTE, SHAFTS & CONNECTIONS KEY PLAN
63 J009-AJ-GUILS1ZZ-PLN-DR-C-10514 P02 TRANSFER TUNNEL ROUTE LONG SECTION
67 J009-AJ-GUILS1ZZ-PLN-DR-C-10519 P05 SHAFT E4A GENERAL ARRANGEMENT AND SECTIONS
68 J009-AJ-GUILS1ZZ-PLN-DR-C-10520 P05 SHAFT E4 GENERAL ARRANAGEMENT AND SECTIONS
71 J009-AJ-GUILS1ZZ-PLN-DR-C-10508 P03 CONSTRUCTION WORKSITE KEY PLAN
72 J009-AJ-GUILS1ZZ-PLN-DR-C-10509 P03 CONSTRUCTION WORKSITE SHEET 1 OF 3
73 J009-AJ-GUILS1ZZ-PLN-DR-C-10510 P03 CONSTRUCTION WORKSITE SHEET 2 OF 3
74 J009-AJ-GUILS1ZZ-PLN-DR-C-10511 P03 CONSTRUCTION WORKSITE SHEET 3 OF 3
75 J009-AJ-GUILS1ZZ-PLN-DR-E-10390 P02 ILLUSTRATIVE ENVIRONMENTAL MASTERPLAN
Appendix 1.1 Scoping Report (Part 1 of 4)
Appendix 1.1 Scoping Report (Part 2 of 4)
Appendix 1.1 Scoping Report (Part 3 of 4)
Appendix 1.1 Scoping Report (Part 4 of 4)
Appendix 1.2 Scoping Opinion from Surrey County Council
Appendix 1.3 Planning Application Drawings
Appendix 6.1 Dust risk assessment
Appendix 6.2 Odour Impact Assessment
Appendix 6.3 Odour management principles
Appendix 7.1 Acoustic Terminology
Appendix 7.3 Baseline Noise Survey
Appendix 7.4 Representative background sound level
Appendix 7.5 Noise Model Inputs
Appendix 8.1 Historic Environment Gazetteer
Appendix 8.2 Heritage Baseline Assessment (Part 1 of 2)
Appendix 8.2 Heritage Baseline Assessment (Part 2 of 2)
Appendix 8.3 Archaeological Investigations Reports (Part 1 of 2)
Appendix 8.3 Archaeological Investigations Reports (Part 2 of 2)
Appendix 8.4 Written Schemes of Investigation
Appendix 8.5 Key Consultation with Stakeholders
Appendix 9.1 Criteria for Landscape and Visual Impact Assessment
Appendix 9.2 Visual assessment schedules
Appendix 9.3 Photographs from representative viewpoints (Part 1 of 2)
Appendix 9.3 Photographs from representative viewpoints (Part 2 of 2)Appendix 9.4 Type 3 Visualisations and Technical Methodology (Part 1 of 4)
Appendix 9.4 Type 3 Visualisations and Technical Methodology (Part 2 of 4)
Appendix 9.4 Type 3 Visualisations and Technical Methodology (Part 3 of 4)
Appendix 9.4 Type 3 Visualisations and Technical Methodology (Part 4 of 4)
Appendix 9.5 Arboricultural impact Assessment
Appendix 9.6 Meeting with Surrey County Council Landscape Officer
Appendix 10.1 Legislative compliance report
Appendix 10.2 Surrey Biodiversity Information Centre (SBIC) data request 2019
Appendix 10.3 Habitat Survey Report
Appendix 10.4 Amphibian Survey Report
Appendix 10.5 Bat Roost and Activity Survey Reports (Part 1 of 2)
Appendix 10.5 Bat Roost and Activity Survey Reports (Part 2 of 2)
Appendix 10.6 Otter and Water Vole Survey Report
Appendix 10.7 Breeding Birds and Barn Owl Survey Report
Appendix 10.8 Fish Data Search 2019
Appendix 10.9 Reptile Survey Report
Appendix 10.11 Terrestrial Invertebrate Survey Report
Appendix 10.12 Aquatic Macroinvertebrate Survey Report
Appendix 10.13 Aquatic Macrophyte Survey Report
Appendix 10.14 Habitat and Landscape Management Plan
Appendix 10.15 Scoping of potential impacts on ecological features
Appendix 10.16 Invasive Species Survey Report
Appendix 11.1 Landfill and Outfall Stability Assessment (Part 1 of 3)
Appendix 11.1 Landfill and Outfall Stability Assessment (Part 2 of 3)
Appendix 11.1 Landfill and Outfall Stability Assessment (Part 3 of 3)
Appendix 11.2 Transfer Tunnel Settlement Risk Assessment (Part 2 of 3)
Appendix 11.2 Transfer Tunnel Settlement Risk Assessment (Part 3 of 3)
Appendix 11.3 Outline Remediation Strategy-MainReport
Appendix 11.3 Outline Remediation Strategy-Appendix A-(Part1of2)
Appendix 11.3 Outline Remediation Strategy-Appendix A-(Part2of2)
Appendix 11.3 Outline Remediation Strategy-Appendix B
Appendix 11.3 Outline Remediation Strategy-Appendix C
Appendix 11.3 Outline Remediation Strategy-Appendix D
Appendix 11.3 Outline Remediation Strategy-Appendix E
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part1of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part2of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part3of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part4of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part5of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part6of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part7of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part8of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part9of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part10of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part11of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part12of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part13of14)
Appendix 11.3 Outline Remediation Strategy-Appendix F-(Part14of14)
Appendix 11.3 Outline Remediation Strategy-Appendix G
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part1of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part2of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part3of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part4of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part5of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part6of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part7of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part8of9)
Appendix 11.3 Outline Remediation Strategy-Appendix H-(Part9of9)
Appendix 11.3 Outline Remediation Strategy-Appendix I
Appendix 11.4 Construction Over and Piling Through Risk Assessment (Part 1 of 4)
Appendix 11.4 Construction Over and Piling Through Risk Assessment (Part 2 of 4)
Appendix 11.4 Construction Over and Piling Through Risk Assessment (Part 3 of 4)
Appendix 11.4 Construction Over and Piling Through Risk Assessment (Part 4 of 4)
Appendix 11.5 Quantitative Groundwater Risk Assessment P20
Appendix 12.1 Flood Risk Assessment (Part 1 of 3)
Appendix 12.1 Flood Risk Assessment (Part 2 of 3)
Appendix 12.1 Flood Risk Assessment (Part 3 of 3)
Appendix 12.2 Drainage Strategy (Part 1 of 2)
Appendix 12.2 Drainage Strategy (Part 2 of 2)
Appendix 12.3 Detailed Water Framework Directive Compliance Assessment
Appendix 14.1 Long list and shortlist of Developments
Figure 1.1 Environmental Constraints
Figure 6.3 Assessed odour receptor locations
Figure 8.1 Designated Historic Environment Assets
Figure 8.2 Non-Designated Historic Environment Assets
Figure 8.3 Historic Landscapes
Figure 9.1 Landscape Character Areas
Figure 9.2 Landscape Constraints and Visual Receptors
Figure 9.3 Landscape townscape character receptors
Figure 10.3 Phase 1 Habitat Survey
Figure 10.4 Non Statutory Sites
Figure 10.5 Invasive Non-Native Species
Figure 10.6 Data Species Record
Figure 11.1 Geology and GI Exploratory Locations (Part 1 of 6)
Figure 11.1 Geology and GI Exploratory Locations (Part 2 of 6)
Figure 11.1 Geology and GI Exploratory Locations (Part 3 of 6)
Figure 11.1 Geology and GI Exploratory Locations (Part 4 of 6)
Figure 11.1 Geology and GI Exploratory Locations (Part 5 of 6)
Figure 11.1 Geology and GI Exploratory Locations (Part 6 of 6)